Water Efficiency Project

In 2018, Northern Region Water Board (NRWB) received financial assistance from the European Investment Bank (EIB) to implement the Water Efficiency Project aimed at increasing reliable water supply for Mzuzu city and Ekwendeni township. The goal of the project was to improve socio-economic growth through increase in access to potable water targeting 345,450 residents in Mzuzu city and 55,400 residents in Ekwendeni by 2030. The main project components were: construction of Ekwendeni Water Treatment Plant (WTP) with a capacity of 13,200 m3; construction of a water storage tank with capacity of 1,000m3 at Chinungu Hill and installation of pumping mains from the WTP; installation of a 3.5 Km long pumping mains from the WTP to Bobo Tank; installation of a distribution pipeline; installation of a booster pump at MBC reservoir tank and an 8.5 Km long pumping mains from the WTP; and installation of a booster pump at Lusangazi. The total cost of the project was estimated at EUR 20.5 million. NRWB hired Matex International as the consultant to conduct an ESIA for the project.

Jenda and Chilumba Water Supply and Sanitation Project

NRWB implemented the Water Supply and Sanitation Project for Jenda in Mzimba and Chilumba in Karonga. The project aimed at expanding and rehabilitating Jenda and Chilumba water supply schemes to meet its current and future water supply demand by improve supply and access to potable water, and improve sanitation for the residents. The main project activities were:

Chilumba Water Supply Scheme

The NRWB hired Matex International as a Consultant to conduct an ESIA for the project.

Water Efficiency Project (Two River Intake Structures)

The NRWB, with support from the European Investment Bank (EIB), implemented the Water Efficiency Project with the aim of increasing reliable water supply for Mzuzu city and Ekwendeni township. This component of the project involved construction of two intake weirs across the Lunyangwa River, one at the Mzuzu Water Treatment Plant (WTP) and the other at the Ekwendeni WTP. Initially, the existing weirs were temporary structures and were made of sandbags to intercept water that was then abstracted through pumping to the water treatment works. This resulted in the significant loss of water by passing around or under the weir. This necessitated the NRWB to construct the new intake weirs with reinforced concrete to enable increased water abstraction and increasing the supply capacity by about 95%. The total costs for implementing the Ekwendeni and Mzuzu weir projects were estimated at €165,000.00 and €65,000.00 respectively.

The NRWB hired a consultant to conduct an ESIA for the proposed project in 2018. Due to come challenges, the project was not implemented as the ESIA did not address some issues with other stakeholders. In 2021, NRWB hired Matex International to update the ESIA by addressing the issues that posed challenges on the implementation of the project.